In 1996, we began construction activities to develop
the Alleco Stone facilities near Phoenix, Arizona. We completed initial
development of the extraction pit area and constructed a 600-ton per hour
aggregate processing plant which is equipped to crush, screen, and wash
aggregate products. By 1998 the sand & gravel operation was profitable
and growing market conditions justified modifications and expansion. We
are now adding additional crushing and washing plants and equipment to
increase production by more than 200% while expanding capabilities to
produce custom specification materials. Our plant is capable of
manufacturing a wide spectrum of aggregate materials ranging from sand
products to course aggregates. Virtually every product that is typically
specified for highway and building construction, in the Phoenix area, will
be manufactured at our facility. The Plant also manufactures special
products for markets such as golf courses and sports complexes.
Alleco has furnished special root zone materials for
projects such as the Bank One Ball Park. The sand reserve we control has
the distinction of approval, by the U.S. Golf Association. This approval
recognizes the sand as meeting specialized specifications for various golf
course and sporting complex uses.
In June of 1997, Alleco entered into a twelve-year
contract to supply sand and gravel requirements to United Metro Materials,
Inc. This contract provided for the construction of a concrete batch
plant on the Alleco site and further provided that Alleco would supply
United Metro's aggregate requirements for the operation of this concrete
plant. Construction of the plant facility was completed in July of 1997
and daily concrete production continues from this plant. United Metro was
the largest producer of sand and gravel and concrete products in the
greater Phoenix area. Recently United Metro was acquired by Rinker
Materials, who with this acquisition has become the second largest
aggregate producer and the fifth largest concrete producer in the
country. Acquisition of this contract relationship with Rinker represents
a substantial and positive factor in the Alleco development plan.
Additionally, Alleco developed a relationship with Otto Trucking to haul
sand and gravel materials and participate in Alleco’s marketing effort.
This relationship is also notable in that Otto is the largest trucking
contractor in the Phoenix area. Development of these two relationships
created assurance that the Alleco expansion program will be justified and
successful.
During the same period Alleco designed and constructed
this unique, high production excavating system to service its raw
material requirements. The system reached out approximately 800 feet and
could dig up to 100 feet below the water level. Changing the positions of
the skyline, which supports the 10 to 12 cubic yard drag bucket, could be
accomplished within minutes by virtue of a track mounted mobile boom which
mobilizes the tail anchor end of the skyline and the bucket haul back
lines. This mobile system was a versatile excavating system that could
dig in a radius of approximately 240 degrees with an overall pit diameter
in excess of 1500 feet. This excavating process allowed Alleco to recover
its mineral reserve below the water table and open the facility as a
viable long-term resource. The dragline operation also established an
initial lake consistent with the Lake Alleco Development Plan and provided
conditions for the next phase of mining and lake development, requiring a
dredging operation.
Construction of the Alleco facility is 95% complete.
Construction and installation of the dredging operations represent the
final plant modification required to reach our goals. This installation
places into production a floating 14” dredge that will ultimately reduce
expenses from our most costly maintenance area. The operating and
maintenance expenses saved by this dredge are generated in the mineral
extraction pit and the roadway maintained for transportation of raw
product to the plant. Reductions in cost are generated by elimination of
daily road maintenance and elimination of the dragline operation, one
hydraulic excavator, two rubber tired loaders, and three dump trucks.
This manpower and equipment is replaced by the 14” dredge that pumps 6,000
gallons of water to the plant each minute and will deliver nearly 500 tons
of 8” minus aggregate feed to the plant each hour.
In conjunction with the dredge and feed by pipe, we are
installing a classifying tower and equipment which will increase sand
production by nearly 300% and eliminate the need for screening ¼” minus
product (which is the slowest and most expensive grade of product to
screen). Long term savings over conventional excavating and haul
operations justify the investment as the market grows in the Phoenix West
Valley. The dredge operation will expand our mineral reserve by allowing
more efficient extraction of usable mineral and the ability to use,
otherwise wasted fines from our overburden, in dry sub base products.
We are completing construction of a 300-ton per hour
asphalt batch plant to produce bituminous concrete paving materials. This
plant is also 95% complete. We anticipate asphalt production to begin in
2003. Construction and development activities in the Phoenix West Valley
have already produced demand for this facility. Growing demand for
material should at least triple Alleco sales over the next two years and
with more than 240 million tons of sand and gravel reserve, Alleco can
service this growing demand for many decades.